North Highway 47 Sidewalks Update
Last item for navigation
Posted on 07/06/2021
                                                                                                                                           PW2 PW3 pw1PW4 PW5 PW6

August 18 Update:
• Culvert extensions are complete
• Rock base is being laid down in preparation for concrete
• Grading is being done to meet ADA requirements
• Warrenton Street Department worked to bring the sewer manholes and water meters to grade with the sidewalks.

Construction Company: RL Persons
Engineer: CMT

  • This is a “BUY AMERICA” job.
  • Tree clearing is at about 90% complete.
  • Purpose of the tree clearing was to set sidewalk back from highway and prevent interference with storm drains and allow for future expansion and widening of highway 47.
  • Approx. 50% of driveway and road crossings on the West side of 47 are complete.
  • Currently working on entrances and exits at McDonalds/Mobile gas station/AT&T.
  • Cuts for crosswalks made at Walmart Entrance/Exit.